House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
HOUSE CONSTRUCTION 192 houses have been completed, while the construction of 87 house units are ongoing and in full swing.House Construction refers to the number of houses completed or under construction. SITE DEVELOPMENT Site development is nearing completion at 99%.Site Development covers site clearing, grading, roads, utilities, open parking, and related work. AMENITIES The Clubhouse, […]
House Construction 188 houses have been completed, while the construction of 45 house units are ongoing and in full swing. Site Development is fully completed Amenities The Clubhouse, Pool, Playground, Basketball Court, Gate Guardhouse, and Boulevard Landscape have been completed. The Town Plaza is set to be completed by Q4 2024. Turnovers 97 units have […]
TURNOVERS 3 house units have been turned over. HOUSE CONSTRUCTION 137 houses have been completed, while the construction of 100 house units are ongoing and in full swing. AMENITIES The guardhouse, gate, and boulevard landscape have been completed, while the basketball court and clubhouse are set to be completed by Q1 2023. SALES 100 units […]
We use cookies to improve your experience on https://ajoya.com.ph. Click “I accept” to let us know you’re okay with our cookie policy.