Ajoya Capas Construction Updates Q1 2023
House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
Ajoya Pampanga Construction Updates Q4 2022
TURNOVERS Property turnovers are set to commence in Q1 2023. HOUSE CONSTRUCTION 55 house units have been constructed, while the construction of 107 house units are ongoing and in full swing. AMENITIES The guardhouse and the boulevard landscape are completed. The clubhouse, basketball court, pool, and playground are set to be completed in Q1 2023. […]
Ajoya Cabanatuan Construction Updates as of Q2 2021
Site Development Installation of the perimeter fence is eyed to be fully completed by Q3 of this year.
Ajoya Capas Construction Updates Q4 2021
TURNOVERS First batch of property turnovers is set to commence in Q1 2022. Need assistance in funding your Ajoya Capas property? Read more about our home loan offerings and services through this LINK.